#7 Plastering


November 06, 2019

 Busy busy busy today, the last of the rough-in tradies were very busy completing the last of their individual parts to this puzzle, meanwhile the truck delivering the gyprock was delayed some four hours, so we had five tradies sitting around playing on their iPhones etc!!

When the  gyprock arrived it was go go go, and the ceiling and walls went up so quickly I felt that I was on the Block!!,  the following day we saw all the plastering completed as well as some finer A/C finishings in the ceiling.

The space now looks like a room soon to be a gallery, plaster setting is to start tomorrow and should be completed by close of Friday.

 

       